| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
p2024_018 / 04 Rev A
p2024_018 / 05
Reason: To define the permission in accordance with Policy SWDP1 and SWDP2 of the South Worcestershire Development Plan and the National Planning Policy Framework. |
| Before the first use/occupation of the development hereby permitted a scheme of landscaping shall be submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:-
(i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread.
(ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas.
(iii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants.
(iv) a written specification outlining cultivation and other operations associated with plant and grass establishment.
(v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting.
All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner.
The planting shall be maintained in accordance with the approved schedule of maintenance. Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the first use/occupation of the development hereby permitted a plan indicating the positions, design, materials and type of boundary treatment to be erected shall be submitted to and approved in writing by the local planning authority The boundary treatment shall be completed before the first use/occupation of the development hereby permitted. Development shall be carried out in accordance with the approved details.
Reason - To protect the amenities of properties and ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan and the relevant aims and objectives of the National Planning Policy Framework. |
| A bat box shall be installed within the land ownership of the site (e.g. Ibstock enclosed bat box, Habibat bat box, Schwegler Wall-mounted Bat Shelter 2FE, Schwegler 2F Bat Box). The box should be installed at least 4m above ground-level, and not placed above windows. The roosting feature shall be installed before the first use of any part of the development.
Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan and the relevant aims and objectives of the National Planning Policy Framework.
|
| Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any order revoking, re-enacting, substituting, amending, extending, consolidating, replacing or modifying that Order), nothing in article 3, Schedule 2 to that order shall operate so as permit any development specified in Part 1 Class E (buildings etc incidental to the enjoyment of a dwellinghouse) and Part 2, Class A (Gates, fences, walls etc) of the said schedule and no such development shall be carried out at any time without an express grant of planning permission under Part III of the Town and Country Planning Act 1990.
Reason: To preserve the rural characteristics of the area and setting of the adjoining listed building and to comply with South Worcestershire Development Plan policies SWDP1, SWDP6, SWDP21, SWDP24 and SWDP25 and the relevant aims and objectives of the National Planning Policy Framework.
|
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |