| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
Block Plan 09/2024/02h Rev A
Location Plan 09/2024/02g Rev A
Attic floor plan as existing 09/2024/02f
Ground floor plan as proposed 09/2024/02b Rev A
Elevations as proposed 09/2024/02a Rev D
Joinery details 1 09/2024/02i Rev B
Joinery details 2 09/2024/02j Rev A
Ground floor plan as existing 09/2024/02e
Mezzaine floor plan as proposed 09/2024/02c Rev C
Elevations as existing 09/2024/02d
Reason: To define the permission in accordance with Policy SWDP1 and SWDP2 of the South Worcestershire Development Plan and the National Planning Policy Framework. |
| In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported immediately to the Local Planning Authority. The applicant is advised to immediately seek the advice of an independent geo-environmental consultant experienced in contaminated land risk assessment, including intrusive investigations and remediation.
No further works should be undertaken in the areas of suspected contamination, other than that work required to be carried out as part of an approved remediation scheme, unless otherwise agreed by the Local Planning Authority, until requirements 1 to 4 below have been complied with:
1. Detailed site investigation and risk assessment must be undertaken by competent persons in accordance with the Environment Agency's 'Land Contamination: Risk Management' guidance and a written report of the findings produced. The risk assessment must be designed to assess the nature and extent of suspected contamination and approved by the Local Planning Authority prior to any further development taking place.
2. Where identified as necessary, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
3. The approved remediation scheme must be carried out in accordance with its terms prior to the re-commencement of any site works in the areas of suspected contamination, other than that work required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority.
4. Following completion of measures identified in the approved remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be produced and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings on site.
Reason: To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors and in accordance with SWDP21 and SWDP31 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The Development hereby approved shall not be brought into use until the vehicular parking facilities as shown on Drawing 09/2024/02h Rev A are provided. This area shall thereafter be retained for the purpose of parking a vehicle only.
Reason: In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway and in accordance with SWDP4 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The Development hereby permitted shall not be brought into use until sheltered and secure cycle parking to comply with the Council’s adopted highway design guide has been provided in accordance with details which shall first be submitted to and approved in writing by the Local Planning Authority and thereafter the approved cycle parking shall be kept available for the parking of bicycles only.
Reason: To comply with the Council’s parking standards and in accordance with Policy SWDP4 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter.
Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The development hereby permitted shall not be occupied/first used until full details of all foul drainage systems to serve the development have been submitted to and approved in writing by the Local Planning Authority. The approved works shall be implemented in accordance with the approved details before the first occupation/use of the development hereby permitted and shall be retained thereafter.
Reason: To ensure development would not result in unacceptable risk of pollution or harm to the environment and to ensure the proposed development does not exacerbate flood risk and deals with surface water run-off from the site in a sustainable manner, in accordance with policies SWDP28, SWDP29 and SWDP 30 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the development hereby permitted is first occupied/used, details of any external lighting to be provided in association with the development shall be submitted to and approved in writing by the Local Planning Authority. The details shall include times when the external lighting will not be switched on. Only external lighting in accordance with approved details shall be provided on the application site. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order with or without modification) there shall be no other external lighting provided on the application site.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP1, SWDP21 and SWDP25 of South Worcestershire Development Plan (2016) and to ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The development hereby approved shall proceed in strict accordance with the recommendations outlined in Chapter 6.5.1 'Proposed mitigation measures' and 6.5.2 'Proposed compensation measures' of the Bat Survey Report (dated 3rd December 2024) by Breakwell Ecology.
Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan and the relevant aims and objectives of the National Planning Policy Framework.
|
| The holiday let unit/visitor accommodation hereby approved shall be occupied for holiday purposes only and shall not be occupied as a person or persons’ sole, or main place of residence.
Reason: The proposed unit/visitor accommodation would be situated in the open countryside, outside any defined settlement boundary where new residential development will be strictly controlled. The proposed unit/accommodation is only acceptable as a holiday let/ tourism development in accordance with policy SWDP12 and/or SWDP35 of the South Worcestershire Development Plan. To grant permission without such a condition would be contrary to policy SWDP2 and/or SWDP12 of the South Worcestershire Development Plan . |
| No person or group of persons shall occupy the holiday accommodation hereby permitted for more than 28 days consecutive days at a time and no same person or group of persons shall occupy the accommodation for more than 156 days in any one calendar year.
The owners/operators of the site shall maintain an up-to date register of the names of all occupiers of the accommodation and of their main home address (i.e. place of residence) and shall make this information available at all reasonable times to the Local Planning Authority.
Reason: To ensure that the development hereby permitted is used for the specific use applied for, to prevent unrestricted residential development and in the interests of ensuring a sustainable pattern of development that also does not unduly increase reliance on the private motor vehicle, in accordance with polices SWDP1, SWDP2, SWDP4, SWDP6, SWDP21, SWDP24 and SWDP25 of the South Worcestershire Development Plan and the relevant aims and objectives of the National Planning Policy Framework. |