| Application Number | W/25/02110/FUL |
| Status | Application Approved |
| Application Valid |
|---|
| 06/10/2025 |
| Consultation End |
|---|
| 27/10/2025 |
| Committee Meeting |
|---|
| N/A |
| Decision |
|---|
| Approval |
| Decision Date |
|---|
| 12/11/2025 |
| Appeal Started |
|---|
| N/A |
| Appeal Decision |
|---|
| N/A |
| Summary | |
| Application Number | W/25/02110/FUL |
| Location Address | Unit 7 George Baylis Road Droitwich Spa WR9 9RB |
| Proposal | Extension to Storage and Distribution area |
| Status | Approval |
| Application Type | Full planning permission |
| Appeal Decision | N/A |
| Important Dates | |
| Application Received Date | 01/10/2025 |
| Application Valid Date | 06/10/2025 |
| Consultation Start Date | 06/10/2025 |
| Site Visited / Site Notice Date | |
| Consultation End | 27/10/2025 |
| Advert Expiry | |
| Committee Date (if applicable) | |
| Committee Agenda | |
| Decision Date | 12/11/2025 |
| Further Information | |
| Expected Decision Level | Delegated |
| Case Officer | Robert Smith |
| Parish | Droitwich Spa |
| Ward | Droitwich West Ward |
| Applicant | Mr Alan Baker, DKS 123 lLtd |
| Agent | Mike Forrester, Forrester Associates |
| Agent Address | Waterloo House Alcester Road Flyford Flavell WR7 4DB |
| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission. Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents – 25:06:01 25:06:02 25:06:04 25:06:05 25:06:06 25:06:07 25:06:08 Reason: To define the permission in accordance with Policy SWDP1 and SWDP2 of the South Worcestershire Development Plan and the National Planning Policy Framework. |
| Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter. Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016. |
| Prior to the development hereby permitted first being occupied, sheltered and secure cycle parking facilities conforming to parking standards set out within Worcestershire's Streetscape Design Guide shall be implemented and thereafter shall be kept available for the parking of bicycles only. Reason: In the interests of providing adequate cycle parking provision within the curtilage of the dwelling house in accordance with SWDP4 & SWDP21 and the aims and objectives of the National Planning Policy Framework (NPPF). |
| Prior to the development hereby permitted first being occupied, accessible car parking facilities for 2 cars conforming to parking standards set out within Worcestershire's Streetscape Design Guide shall be implemented and thereafter shall be kept available for disabled users. Reason: In the interests of providing adequate car parking provision within the curtilage of the dwelling house in accordance with SWDP4 & SWDP21 and the aims and objectives of the National Planning Policy Framework (NPPF). |
| Prior to the occupation of any part of the development hereby permitted details of renewable or low carbon energy generating facilities to be incorporated as part of the development shall be submitted to and approved in writing by the local planning authority. The details shall demonstrate that at least 10% of the predicted energy requirements of the development will be met through the use of renewable/low carbon energy generating facilities. The approved facilities shall be provided prior to any part of the development hereby permitted being first occupied or in accordance with a timetable submitted to and approved by the local planning authority as part of the details required by this condition. Reason: To ensure the proposed development includes sufficient renewable/low carbon energy generating facilities to comply with Policy 27 of the South Worcestershire Development Plan 2016 and the aims and objectives of the National Planning Policy Framework (NPPF). |
| In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported immediately to the Local Planning Authority. The applicant is advised to immediately seek the advice of an independent geo-environmental consultant experienced in contaminated land risk assessment, including intrusive investigations and remediation. No further works should be undertaken in the areas of suspected contamination, other than that work required to be carried out as part of an approved remediation scheme, unless otherwise agreed by the Local Planning Authority, until requirements 1 to 4 below have been complied with: 1. Detailed site investigation and risk assessment must be undertaken by competent persons in accordance with the Environment Agency's 'Land Contamination: Risk Management' guidance and a written report of the findings produced. The risk assessment must be designed to assess the nature and extent of suspected contamination and approved by the Local Planning Authority prior to any further development taking place. 2. Where identified as necessary, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation. 3. The approved remediation scheme must be carried out in accordance with its terms prior to the re-commencement of any site works in the areas of suspected contamination, other than that work required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority. 4. Following completion of measures identified in the approved remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be produced and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings on site. Reason: To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors in accordance with SWDP31 of the South Worcestershire Development Plan 2016 and the aims and objectives of the National Planning Policy Framework (NPPF). |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |
Plans, drawings and material submitted to the council are protected by the copyright acts (section 47, 1988 act). You may only use material which is downloaded and/or printed for consultation purposes, to compare current applications with previous schemes and to check whether developments have been completed in accordance with approved plans. Further copies must not be made without the prior permission of the copyright owner.
Tick here to show you have read and agree with the Copyright Notice.
Document Download Tips
How to reorder or group rows
Click on a column heading for the ability to sort the ‘group’ listing in ascending or descending order by using the up/down arrows. This is useful to sort by ‘name/organisation’.
In addition to consultations with the consultee listed, we will publicise the application in accordance with national requirements and our local policy. This publicity usually takes the form of letters to nearby properties, the posting of site notices and/or the placing of a public notice in our local newspapers.
| Address | Sent | Reply Received |
|---|---|---|
| First Floor Unit 5 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Ground Floor Unit 5 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Lidl George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Unit 1 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Unit 2 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Unit 3 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Unit 4 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 | |
| Unit 5 George Baylis Court George Baylis Road DROITWICH SPA WR9 9RB | 06/10/2025 |
| Name | Organisation | Sent | Reply Due | Reply Received |
|---|---|---|---|---|
| Cllr George Duffy | Droitwich Spa West Ward | 06/10/2025 | 27/10/2025 | |
| Cllr Ms Jennifer Chaudry | Droitwich Spa West Ward | 06/10/2025 | 27/10/2025 | |
| Drainage Engineer | Engineers - S.W. Land Drainage Partnership | 06/10/2025 | 27/10/2025 | |
| Emma Ridley | Economic Development Officer | 06/10/2025 | 27/10/2025 | |
| Highways | County Highways | 06/10/2025 | 27/10/2025 | |
| Mike Hayzelden | Droitwich Spa Civic Society | 06/10/2025 | 27/10/2025 | |
| Mr Mark Keld | Droitwich Town Council | 06/10/2025 | 27/10/2025 | |
| Mr S Bloomfield | Worcestershire Wildlife Trust | 06/10/2025 | 27/10/2025 | |
| Mrs E Marshall | Landscape Officer | 06/10/2025 | 27/10/2025 | |
| Mrs H Fleming | Natural England | 06/10/2025 | 27/10/2025 | |
| Network Rail (Western Region) | Network Rail (Western Region) | 06/10/2025 | 27/10/2025 | |
| WDC Natural Heritage & Biodiversity Officer | WDC Natural Heritage & Biodiversity | 06/10/2025 | 27/10/2025 | |
| Worcestershire Regulatory Services - Cont. Land | Worcestershire Regulatory Services | 06/10/2025 | 27/10/2025 | |
| Worcestershire Regulatory Services - Nuisance | Worcestershire Regulatory Services | 06/10/2025 | 27/10/2025 |
| Constraints List |
| SWDP 5: Urban - Unsurveyed |
| SWDP 2: Development Boundary |
| Wind Turbines |
| Policy Case ELA - WDC/15/EMP. Acorn Catering Equipment, George Baylis Road, Droitwich Spa, WR9 9RB. Demolition of existing buildings and erection of a Class A1 retail foodstore (Lidl) with associated car parking, access, landscaping and associated engineering works. Complete. |
| Contaminated Land |
| Section 106 Agreement |
| CIL002 - Main Urban Area |
| Paper: Droitwich Advertiser - Thursday |
| Landfill Consultation |
| Surface Water: High 1 in 30 extent |
| Surface Water: Low 1 in 1000 extent |
| Surface Water: Medium 1 in 100 extent |
| Railway Line - Case Officer to refer to Network Rail Standing Advice and Matrix |
| Local Wildlife Site |
| Historic Landfill Consultation (within 250m) |
| No associated appeals |