| Condition Details / Information Notes |
| The development hereby permitted must be commenced not later than the expiration of three years from the date of the original permission 17/02210/FUL dated 21/3/18
Reason: To conform with the requirements of Sections 73 and 91 of the Town and Country Planning Act 1990 (as amended). |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
1716/01d
Reason: To define the permission. |
| The development hereby approved shall not be occupied until the first 5 metres of the access into the development, measured from the edge of the carriageway, has been surfaced in a bound material.
REASON: In the interests of highway safety. |
| The development hereby approved shall not be occupied until the access, turning area and parking facilities shown on drawing 1716/01d have been provided. These areas shall thereafter be retained and kept available for their respective approved uses at all times.
Reason: In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway.
|
| This permission does not authorise the applicant to carry out works within the publicly maintained highway since such works can only be carried out by the County Council’s Approved Contractor, Ringway Infrastructure Service who can be contacted by email worcestershirevehicle.crossing@ringway.co.uk. The applicant is solely responsible for all costs associated with construction of the access. |
| The development hereby permitted shall not be occupied/first used until full details of all foul and surface water drainage systems to serve the development have been submitted to and approved in writing by the Local Planning Authority. The approved drainage works shall be implemented in accordance with the approved details before the first occupation/use of the development hereby permitted and shall be retained thereafter.
Reason: To ensure development would not result in unacceptable risk of pollution or harm to the environment and to ensure the proposed development does not exacerbate flood risk and deals with surface water run-off from the site in a sustainable manner, in accordance with policies SWDP28, SWDP29 and SWDP 30 of the South Worcestershire Development Plan. |
| The construction work on the buildings hereby approved shall not be commenced until the precise floor slab levels of each new building, relative to the existing development on the boundary of the application site have been submitted to and approved in writing by the local planning authority. Thereafter the new buildings shall be constructed at the approved floor slab levels.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21, SWDP25 and SWDP 28 of South Worcestershire Development Plan. |
| Before the first use/occupation of the development hereby permitted a scheme of landscaping shall be submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:-
(i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread.
(ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas.
(iii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants.
(iv) a written specification outlining cultivation and other operations associated with plant and grass establishment.
(v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting.
All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner.
The planting shall be maintained in accordance with the approved schedule of maintenance. Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan. |
| Details of the form, colour and finish of the materials to be used externally on the walls and roofs shall be subject to the approval, in writing, of the Local Planning Authority before any construction work on the site commences. All works shall be carried out in accordance with the approved details.
Reason - To ensure that the development is visually satisfactory in accordance with Policy SWDP21 of the South Worcestershire Development Plan. |
| Prior to the occupation of any part of the development hereby permitted details of renewable or low carbon energy generating facilities to be incorporated as part of the development shall be carried out in accordance with the Energy Statement submitted. The details shall demonstrate that at least 10% of the predicted energy requirements of the development will be met through the use of renewable/low carbon energy generating facilities. The approved facilities shall be provided prior to any part of the development hereby permitted being first occupied.
Reason: To ensure the proposed development includes sufficient renewable/low carbon energy generating facilities to comply with Policy SWDP 27 of the South Worcestershire Development Plan 2016. |
| Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter.
Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016. |
| South Worcestershire Councils Community Infrastructure Levy (Non-Strategic Allocation)
The application provides residential housing within the South Worcestershire Development Plan area, therefore the South Worcestershire Councils Community Infrastructure Levy Charging Schedule is applicable.
The applicant should make its proportionate contribution to identified infrastructure in accordance with the South Worcestershire Councils Community Infrastructure Levy Charging Schedule. Transport infrastructure is covered by this Levy and therefore it is essential that the cumulative impact of all development is addressed through the receipt of the contribution(s) as defined in Section 8, Table 1 of the Charging Schedule. |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |
| The development hereby approved shall not be occupied until the access, turning area and parking facilities shown on drawing 1716/01d have been provided. These areas shall thereafter be retained and kept available for their respective approved uses at all times.