| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
KI 5809 1 Existing Plans, Elevations and 3D
KI 5809 2 Existing Block and Location Plan
KI 5809 3 Proposed Site Plan
KI 5809 4 Proposed Block and Location Plan
KI 5809 5 Proposed Plans, Elevations and 3D
KI 5809 6 Proposed Garage
Reason: To define the permission. |
| Prior to the first use/occupation of the development hereby permitted, the details set out in the submitted Water Management Statement shall be fully implemented and remain thereafter.
Reason: To ensure that an appropriate sustainable drainage system is provided to serve the development in accordance with policy SWDP29 of the South Worcestershire Development Plan 2016. |
| The dwelling hereby approved shall not be occupied until the parking and turning area have been provided as shown on drawing KI 5809 Revision 3.
Reason: To ensure conformity with submitted details in compliance with SWDP4. |
| The Development hereby approved shall not be occupied until the first 5 metres of the access into the development, measured from the edge of the carriageway, has been surfaced in a bound material and free of loose stone.
Reason In the interests of highway safety in accordance with SWDP4. |
| Any new access gates shall be set back 5metres from the adjoining carriageway edge and shall be made to open inwards only.
Reason: In the interests of highway safety in compliance with SWDP 4. |
| The Development hereby permitted shall not be first occupied until the proposed garage/dwelling has been fitted with an electric vehicle charging point. The charging points shall comply with BS EN 62196 Mode 3 or 4 charging and BS EN 61851 and the Worcestershire County Council Streetscape Design Guide. The electric vehicle charging points shall be retained for the lifetime of the development unless they need to be replaced in which case the replacement charging point(s) shall be of the same specification or a higher specification in terms of charging performance.
Reason: To encourage sustainable travel and healthy communities. |
| a) Gas protection measures complying with Characteristic Situation 2 as set out in BS8485:2015 and CIRIA C665 as a minimum requirement must be incorporated within the foundations of the proposed structure(s). Following installation of these measures, and prior to the first occupation of the development, a verification report shall be submitted to and approved in writing by the Local Planning Authority. Verification of the installation of gas protection measures must be carried out in accordance with current UK guidance and best practice.
Or
b) A risk assessment should be undertaken to establish whether the proposed development is likely to be affected by landfill or ground gas or vapours. The risk assessment must be provided to and approved in writing by the Local Planning Authority, prior to the commencement of development. The assessment shall be carried out in accordance with current UK guidance and best practice.
c) Where the approved risk assessment (required by condition (b) above) identifies ground gases or vapours posing unacceptable risks, no development shall commence until a detailed remediation scheme to protect the development from the effects of such ground gases or vapours has been submitted to and approved in writing by the Local Planning Authority. Following approval, the remediation scheme shall be implemented on site in complete accordance with approved details unless otherwise agreed in writing by the Local Planning Authority.
d) Following implementation and completion of the approved remediation scheme (required by condition (c) above) and prior to the first occupation of the development, a verification report shall be submitted to and approved in writing by the Local Planning Authority to confirm completion of the remediation scheme in accordance with approved details. Verification of the installation of gas protection measures must be carried out in accordance with current UK guidance and best practice.
REASON: To ensure that the risk to buildings and their occupants from potential landfill or ground gases are adequately addressed. |
| Prior to the first use/occupation of the development hereby permitted, the details of renewable and/or low carbon energy generation measures as set out within the Energy Statement accompanying this permission shall be fully implemented and remain thereafter.
Reason - To ensure the development supports the delivery of low carbon/renewable energy and safeguards natural resources in accordance with policy SWDP27 of the South Worcestershire Development Plan. |
| This permission does not authorise the applicant to carry out works within the publicly maintained highway since such works can only be carried out by the County Council’s Approved Contractor, Ringway Infrastructure Service who can be contacted by email worcestershirevehicle.crossing@ringway.co.uk. The applicant is solely responsible for all costs associated with construction of the access. |
| Positive and Proactive Statement. No problems have arisen in dealing with this application. The planning application sought an acceptable form of development consistent with the requirements of relevant policies and material considerations. No amendments or alterations were therefore required and no further positive or proactive action was deemed necessary. |
| Prior to the commencement of any above ground works, details of the materials to be used in the construction of the external surfaces of the dwelling hereby permitted have been submitted to and approved in writing by the local planning authority. The details to be submitted shall include: -
- a precise specification of the proposed external render
- type, colour, size of roofing materials
The development shall be carried out using the materials as approved.
Reason - To ensure that the new materials are in keeping with the surroundings and/or represent quality design in accordance with policy SWDP21 of the South Worcestershire Development Plan.
|