| Condition Details / Information Notes |
| The development hereby permitted shall be begun before the expiration of three years from the date of this permission.
Reason: To conform with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| Unless where required or allowed by other conditions attached to this permission/consent, the development hereby approved shall be carried out in accordance with the information (including details on the proposed materials) provided on the application form and the following plans/drawings/documents –
Proposed Ground Floor Plan SK01 A
Proposed First Floor Plan SK02
Proposed North & South East Elevation SK03 A
Proposed North & South West Elevations SK04 A
Existing Barn Ground Floor Plan SK05
Existing Barn Front & Rear Elevations SK06
Existing Barn Side Elevations SK07
Proposed Site Plan SK10 A
Existing Site Plan SK11 A
Location Plan SK12 A
Reason: To define the permission in accordance with Policy SWDP1 and SWDP2 of the South Worcestershire Development Plan and the National Planning Policy Framework. |
| No building operations herby permitted shall commence until details of all the external materials to be used in the construction of the development shall be submitted to and approved in writing by the Local Planning Authority.
The development shall not be carried out other than in accordance with the approved details.
Reason: To ensure a satisfactory external appearance of the development and that high quality materials and finishes are used, in accordance with policies SWDP 21 and SWDP 25 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of National Planning Policy Framework.
|
| The Development hereby approved shall not be occupied until the access, parking and turning facilities have been provided as shown on Drawing No. SK10 A.
REASON: To ensure conformity with summited details and to comply with Policies SWDP4 and SWDP21 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The Development hereby approved shall be carried out substantially in accordance with Drawing No. SK10 A.
REASON: To define the permission and to ensure that the development meets the design quality and requirements of the Worcestershire Streetscape Design Guide and to comply with Policy SWDP4 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The Development hereby approved shall not be occupied until the first 5 metres of the access into the development, measured from the edge of the carriageway, has been surfaced in a bound material.
REASON: In the interests of highway safety and to comply with Policy SWDP4 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The Development hereby approved shall not be occupied until sheltered and secure cycle parking to comply with the Council’s adopted highway design guide has been provided in accordance with details which shall first be submitted to and approved in writing by the Local Planning Authority and thereafter the approved cycle parking shall be kept available for the parking of bicycles only.
REASON: To comply with the Council’s parking standardsand to comply with Policy SWDP4 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the commencement of development hereby permitted, details of renewable and/or low carbon energy generation measures shall be submitted to and approved in writing by the Local Planning Authority. The measures shall contribute to at least 10% of the predicted energy requirements of the development. The details to be submitted shall include:-
- the overall predicted energy requirements of the approved development;
- the predicted energy generation from the proposed renewable/low carbon energy measures; and
- an implementation timetable for the proposed measures.
The development shall be carried out in accordance with the approved details.
Reason - To ensure the development supports the delivery of low carbon/renewable energy and safeguards natural resources in accordance with policy SWDP27 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the first use/occupation the development hereby permitted details of a precise specification of the proposed materials for the hard landscaping of the site (including roads, paths, parking areas and other hard surfaces) shall be submitted to and approved in writing by the local planning authority. The hard landscaping of the site shall be completed before the first use/occupation of the development hereby permitted. Development shall be carried out in accordance with the approved details.
Reason - To ensure the proposed development represents high quality design and does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the first use/occupation of the development hereby permitted a scheme of landscaping shall be submitted to and approved in writing by the Local Planning Authority. The landscaping scheme shall include:-
(i) a plan(s) showing details of all existing trees and hedges on the application site. The plan should include, for each tree/hedge, the accurate position, canopy spread and species, together with an indication of any proposals for felling/pruning and any proposed changes in ground level, or other works to be carried out, within the canopy spread.
(ii) a plan(s) showing the layout of proposed tree, hedge and shrub planting and grass areas.
(iii) a schedule of proposed planting - indicating species, sizes at time of planting and numbers/densities of plants.
(iv) a written specification outlining cultivation and other operations associated with plant and grass establishment.
(v) a schedule of maintenance, including watering and the control of competitive weed growth, for a minimum period of five years from first planting.
All planting and seeding/turfing shall be carried out in accordance with the approved details in the first planting and seeding/turfing seasons following the completion or first occupation/use of the development, whichever is the sooner.
The planting shall be maintained in accordance with the approved schedule of maintenance. Any trees or plants which, within a period of five years from the completion of the planting, die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the first use/occupation of the development hereby permitted a plan indicating the positions, design, materials, type of boundary treatment and elevation shall be submitted to and approved in writing by the local planning authority. The boundary treatment shall be completed before the first use/occupation of the development hereby permitted. Development shall be carried out in accordance with the approved details.
Reason - To protect the amenities of properties and ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP21 and SWDP25 of South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The development hereby permitted shall not be occupied/first used until full details of all foul and surface water drainage systems to serve the development have been submitted to and approved in writing by the Local Planning Authority. The approved drainage works shall be implemented in accordance with the approved details before the first occupation/use of the development hereby permitted and shall be retained thereafter.
Reason: To ensure development would not result in unacceptable risk of pollution or harm to the environment and to ensure the proposed development does not exacerbate flood risk and deals with surface water run-off from the site in a sustainable manner, in accordance with policies SWDP28, SWDP29 and SWDP 30 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| Before the development hereby permitted is first occupied/used, details of any external lighting to be provided in association with the development shall be submitted to and approved in writing by the Local Planning Authority. The details shall include times when the external lighting will not be switched on. Only external lighting in accordance with approved details shall be provided on the application site. Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (or any Order revoking or re-enacting that Order with or without modification) there shall be no other external lighting provided on the application site.
Reason - To ensure the proposed development does not have an adverse effect on the character and appearance of the area in accordance with policies SWDP1, SWDP21 and SWDP25 of South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| In the event that contamination is found at any time when carrying out the approved development that was not previously identified it must be reported immediately to the Local Planning Authority. The applicant is advised to immediately seek the advice of an independent geo-environmental consultant experienced in contaminated land risk assessment, including intrusive investigations and remediation.
No further works should be undertaken in the areas of suspected contamination, other than that work required to be carried out as part of an approved remediation scheme, unless otherwise agreed by the Local Planning Authority, until requirements 1 to 4 below have been complied with:
1. Detailed site investigation and risk assessment must be undertaken by competent persons in accordance with the Environment Agency's 'Land Contamination: Risk Management' guidance and a written report of the findings produced. The risk assessment must be designed to assess the nature and extent of suspected contamination and approved by the Local Planning Authority prior to any further development taking place.
2. Where identified as necessary, a detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to identified receptors must be prepared and is subject to the approval of the Local Planning Authority in advance of undertaking. The remediation scheme must ensure that the site will not qualify as Contaminated Land under Part 2A Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
3. The approved remediation scheme must be carried out in accordance with its terms prior to the re-commencement of any site works in the areas of suspected contamination, other than that work required to carry out remediation, unless otherwise agreed in writing by the Local Planning Authority.
4. Following completion of measures identified in the approved remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be produced and is subject to the approval of the Local Planning Authority prior to the occupation of any buildings on site.
Reason: To ensure that the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property, and ecosystems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors and in accordance with SWDP21 and SWDP31 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework. |
| The development hereby permitted shall be carried out in strict accordance with the mitigation (chapter 6) and enhancements (chapter 7) set out in the Great Crested Newt Habitat Suitability Assessment dated 26 February 2025 by Arbor Vitae.
Reason: To ensure the development contributes to the conservation and enhancement of biodiversity within the site and the wider area in accordance with policy SWDP22 of the South Worcestershire Development Plan (2016) and the relevant aims and objectives of the National Planning Policy Framework.
|
| Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any order revoking, re-enacting, substituting, amending, extending, consolidating, replacing or modifying that Order), no (restricted works)(additions, extensions or external alterations) (new windows or other openings) (building or enclosure, swimming or other pool required for a purpose incidental to the enjoyment of the dwelling house) [other than those expressly authorised by this permission] shall be constructed/carried out on the application site following the completion/first use of the development hereby permitted.
Reason: To safeguard the character and appearance of the development and its surroundings, in the interestes of adjoining residential amenity and to ensure a high standard of design in accordance with Policy SWD21 of the South Worcestershire Development Plan (2016) and the relevant provisions of the National Planning Policy Framework, in particular Section 12 - Achieving well-designed places. |
| The applicants attention is drawn to the existence of an agreement made under Section 106 of the Town and Country Planning Act 1990 (as amended), and the restrictions imposed therein. |
| Before undertaking any work on site, all applicants must determine if Severn Trent has any assets in the vicinity of the proposed works. This can be done by accessing our records at www.digdat.co.uk
Severn Trent Water advise that even if our statutory records do not show any public sewers within the area you have specified, there may be sewers that have been recently adopted under The Transfer of Sewer Regulations 2011.
Public sewers and Water mains have statutory protection and may not be built close to, or diverted without consent, consequently you must contact Severn Trent Water to discuss your proposals. Severn Trent will seek to assist you obtaining a solution which protects both the public sewer and the proposed building |